This paper considers single-machine scheduling problems in which a given solution, i.e., an ordered set of jobs, has to be improved as much as possible by re-sequencing the jobs. The need for rescheduling may arise in different contexts, e.g., due to changes in the job data or because of the local objective in a stage of a supply chain that is not aligned with the given sequence. A common production setting entails the movement of jobs (or parts) on a conveyor. This is reflected in our model by facilitating the re-sequencing of jobs via a buffer of limited capacity accessible by a LIFO policy. We consider the classical objective functions of total weighted completion time, maximum lateness and (weighted) number of late jobs and study their complexity. For three of these problems, we present strictly polynomial-time dynamic programming algorithms, while for the case of minimizing the weighted number of late jobs NP-hardness is proven and a pseudo-polynomial algorithm is given.

Optimally rescheduling jobs with a Last-In-First-Out buffer / G. Nicosia, A. Pacifici, U. Pferschy, J. Resch, G. Righini. - In: JOURNAL OF SCHEDULING. - ISSN 1094-6136. - (2021). [Epub ahead of print] [10.1007/s10951-021-00707-5]

Optimally rescheduling jobs with a Last-In-First-Out buffer

G. Righini
2021

Abstract

This paper considers single-machine scheduling problems in which a given solution, i.e., an ordered set of jobs, has to be improved as much as possible by re-sequencing the jobs. The need for rescheduling may arise in different contexts, e.g., due to changes in the job data or because of the local objective in a stage of a supply chain that is not aligned with the given sequence. A common production setting entails the movement of jobs (or parts) on a conveyor. This is reflected in our model by facilitating the re-sequencing of jobs via a buffer of limited capacity accessible by a LIFO policy. We consider the classical objective functions of total weighted completion time, maximum lateness and (weighted) number of late jobs and study their complexity. For three of these problems, we present strictly polynomial-time dynamic programming algorithms, while for the case of minimizing the weighted number of late jobs NP-hardness is proven and a pseudo-polynomial algorithm is given.
Complexity; Dynamic programming algorithms; Rescheduling; Scheduling; Sequence coordination; Supply chain sustainability
Settore MAT/09 - Ricerca Operativa
2021
21-set-2021
Article (author)
File in questo prodotto:
File Dimensione Formato  
50 - 2021 JoS - LIFO rescheduling.pdf

accesso aperto

Tipologia: Publisher's version/PDF
Dimensione 682.1 kB
Formato Adobe PDF
682.1 kB Adobe PDF Visualizza/Apri
Pubblicazioni consigliate

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/2434/870216
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus 2
  • ???jsp.display-item.citation.isi??? 3
social impact